TIMELINE
Phase I [Backbone Cabling]
May 10-17
Trenching to add Conduit between KHIC/HPCC and HPCC/Timken
May 17-27
Additional fiber (Single Mode) to be installed between KHIC/HPCC, HPCC/Timken, and Timken/KHIC
Phase II [Internal Wiring]
May 10-27 - Timken Physical Education Bldg.
May 17-June 4 - McCready Residence Hall
June 1 18 - McMaster Residence Hall
June-July - Tolerton & Hood Hall of Science
Phase III [Network Electronics]
May 28-June 1
Upgrade network electronic hardware in all administrative and academic buildings
July 1-4
Residence Halls (McCready & McMaster back online after rewiring and network upgrade)
Phase IV [Wireless]
June - KHIC / McMaster / McCready / Cunningham
July August - Academic Bldgs. (TBA)
Dec May ’05 - Other Residence Halls
Phase V [Internal Wiring]
Dec. July ’05
Continuation of internal wiring for Cunningham / Eells / Physical Plant / Chapman / HPCC(old) / Ketcham / Adult Studies / Health Center
|